| |
| ICI
worked on a project at Antelope Valley Station
for Basin Electric Power Cooperative to replace two Feedwater
Heaters in Unit Two during their Spring Outage starting April
15.
The project
involves removal of existing piping from two feedwater heaters
located in the plant, and replacing them with two new
heaters. These
heaters are about 5.5’ in diameter. One is
33’ long and 47 tons. The other feedwater heater is
45’ long
and 66 tons.
The heater
floor in the plant is 165’ above grade, and
we have to reach approximately 90’ from the center pin
of the crane to the platform where the heaters will exit and
enter the building.
We
are assembling a Manitowoc 4100 Crane with a ringer attachment
to perform this work. Cranes
are normally on tracks but because this crane has to reach
out 90' over the the top of the turbine building, it has
to be put on a ringer. A ringer is a track that is anchored
down
to
the
ground.

Iron
Workers Install Counter Weights
on the Manitowoc 4100 Crane
|
This crane
has 300’ of
main boom in the rig. It also uses an auxiliary support
crane. The auxiliary support crane is a 75 ton American
Truck Crane,
supplied by Borsheim Crane Service of Williston. It took
approximately
five days to assemble the crane and ringer for this job.
The crane was shipped to the job in 28 loads. |
| |

American
Truck Auxiliary Support Crane |

Manitowoc
4100 Crane with Ringer |
|
| |
We
have opened up a section of wall on the power plant and removed
some sheeting girts. We will install supplementary steel
to support the loads involved, and erect a platform to land
the heaters on to make the picks. When complete, the platform
will be situated in front of the opening in the power plant
wall.

Construction
of Heater Platform
|
|
| |
In
the picture to the right, the platform
to land the heaters on has been erected.
View
of Platform from the Heater Floor
|
|
| |

New
Feedwater Heaters at Work Area
|
|
| |
Pipefitters
Removing Trim Piping from Old Feedwater Heater
|
At this point,
we have started cutting the piping away from the old heaters. |
| |
In
the picture to the right we
are removing the old feedwater heaters from the power plant.
|
| |

Crane
Removing Old Feedwater Heaters
|
|
|
|
| |
Crane
Lifting New Feedwater Heaters to the Platform
|
|
|
|
| |
Here
we are working
on the main piping connection welds, trim piping and level
control instrumentation on the feedwater
heaters.
APi Construction
Company is installing the new heater insulation and lagging.
Visit their website
at www.apiconst.com |
| |

Level
Control Instrumentation
|
|

Trim Piping and Insulation
|
|
| |

Old
Feedwater Heater |
Along with
moving these heaters, the project involves cutting and machining
the pipe for the heaters, welding the new heaters to the
existing pipe, stress relieving the pipe, removing and installing
insulation and lagging (by APi
Construction, Co.), and reinstalling
the trim and instrumentation piping.
|
| |

New
Feedwater Heater
|
Feedwater
heaters are used to raise the temperature of the water from
the condenser that is sent back to the boiler to make steam.
This improves the thermodynamic efficiency of the system, and
also helps to avoid thermal shock to the boiler metal when
the feedwater is introduced back into the steam cycle. The
feedwater heater walls are 2" thick in order to withstand
high pressure. As time goes on, these heaters wear out and
need
to be replaced. Unfortunately,
it is not always easy to access these heaters for replacement,
as is the case with this project. |
| |

Typical Coal Fired Boiler Schematic
|
| |
|
|