Vipond
Fire Protection - Ottawa Branch was the contractor selected
for the design and installation of both the temporary
and new sprinkler systems in the Library of Parliament. The
building dates back to 1859. It is considered Canada’s
most highly recognized heritage building and is a national
treasure.
Now, a
century and a half later, it is undergoing a conservation,
rehabilitation and restoration program. The
work and materials
have been designed with the intent of lasting for fifty
years.
The complex
design involved architects, engineers, heritage and government
personnel, and took almost four years to prepare.
The inside
rehabilitation includes complete refurbishment of the
existing building and the addition of a mechanical room to
be excavated thirty feet below the structure. This in itself
was a challenge
as the excavation consisted of solid rock that had to be removed
using mining techniques.
The outside
rehabilitation of the stone requires 10 levels of temporary
structural scaffolding enclosed by a special fabric to shelter
both workers and masonry during varying weather conditions.
This scaffolding is protected by a temporary sprinkler system
on each level that is fed through a dry Siamese connection.
The inside also has numerous levels of scaffolding that is
protected by a temporary pre-action sprinkler system to avoid
accidental discharges. |