JAMAR
COMPANY IS CURRENTLY WORKING ON ST. MARY'S DULUTH CLINIC EXPANSION
| |
St.
Mary's Duluth Clinic
|
The
Jamar Company is currently working on St. Mary's Duluth Clinic
new 250,000 square foot cancer center.
This expansion project
is
a registered
LEED project and is considering pursuit of SILVER certification.
M.A. Mortenson of Minneapolis, MN is the construction manager
for this facility which has a total construction budget of
$51 million of which $12 million represents work secured by
the Jamar Commercial Mechanical Division and $1.8 million in
work secured
by
the Jamar
Architectural
Division.
LEED, or Leadership
in Energy and Environmental Design, was created to define “green
building” by
establishing a common standard of measurement; promoting integrated,
whole-building design practices; recognizing environmental
leadership in the building industry and raising consumer awareness
of
green building benefits.
The Weidt Group has performed the building modeling, incorporating
several energy saving solutions as part of Jamar’s value
engineering process, helping this project to earn the LEED
classification. Energy saving solutions include;
working with
water
reduction and efficiency; chemical free water treatment system;
installing high efficiency variable frequency drive motors; increased
boiler and chiller efficiencies; CO2
monitoring and control of outside air.
The
Smallest of Five Custom Air Handling Units Installed
by Jamar
|
Jamar has just
completed 18 months of MEP pre construction as part of its design/assist
mechanical scope. AutoCAD and QuickPen 3D software were used for
the MEP coordination drawings. Currently, Jamar crews are working
on plumbing, HVAC piping and ductwork, roofing, siding and waterproofing
systems. Completion is scheduled for March 2006 with 34,000 of
97,000 estimated man-hours worked to date.
Mechanical
system highlights include:
- Two
200 HP low pressure steam boilers with fuel oil back-up.
- 820
ton variable primary cooling loop with one Trane
centrifugal chiller and one induced draft, cross flow
cooling
tower both utilizing variable frequency drives.
- Dolphin
chemical free water treatment system for HVAC condenser
water.
- Variable
air volume air distribution system utilizing five custom
double wall air handlers with over 200,000
CFM in all.
- Medical
gas system including oxygen, medical air and vacuum.
- 20,000
linear feet of snow melt tubing.
- Medical
chillers with emergency backup for three MRIs, two CRTs
and two linear accelerators.
- Johnson
Controls direct digital control/energy management system
including lighting controls.
Architectural system highlights include:
- 35,000
s/f below grade foundation waterproofing.
- 8,000 s/f hot applied terrace waterproofing
including a high grade terrace paver system.
- 9,000
s/f in traffic coatings.
- 786,000
s/f ballasted and fully adhered EPDM systems.
- 3,000
s/f high performance architectural louvers.
- 2,500
s/f aluminum plate column, soffit and skywalk panels.
- 10,000
s/f field assembled metal wall panel systems.
- 2,100
s/f field assembled soffit panel systems.
The Architectural Division has been
tasked with providing all the necessary AutoCAD coordination
drawings and computerized
estimating for the various components.
|
| |
HVAC
Cooling Water Pipe Installation
|
|
Electrical
Conduit
|
|
|
| |
| It was a
major undertaking blasting the ledge work to accommodate underground
installation of the HVAC cooling water pipe by Jamar and the
electrical conduit by APi Electric. |
| |
St.
Mary's Duluth Clinic - South Elevation
|
A number of
APi Group companies are working together to deliver the overall
mechanical work scope:
- Viking
Automatic Sprinkler will install a wet/dry sprinkler system
complete with six (6) double-interlock pre-action systems
and a 200 HP fire pump.
- APi
Supply/ASDCO is supplying man-lifts and temporary heat.
- APi
Electric will perform electrical and low voltage work.
- Lejune
Steel is providing building structural steel.
|
Rendering
of St. Mary's Duluth Clinic
|
|
| |
Jamar
is staffed with skilled personnel capable of tackling commercial
projects including plumbing, HVAC, refrigeration, temperature
controls, water balancing and ventilation systems. Jamar's
Architectural Division design, furnish and install all
types of wall and roofing systems, including new construction,
repairs and re-roofing projects, and waterproofing systems. They
are committed to delivering
projects safely on time and with the highest degree
of quality to each of their customers.